Disposal of dregded materials at deep water at the head of the Ranfjord

Report
Year of publication
2015
External websites
Cristin
Arkiv
Contributors
Andre Staalstrøm, Magdalena Kempa

Summary

Here we consider the discharge of a total of 100 000 tonnes of clean dredged materials in a position at the head of the Ranfjord where it is 300 m deep. In the model, the discharge is modelled as a continuous flow distributed evenly from the surface to the bottom. The discharge takes place in a total of 62 days. In reality, the discharge will have a more patchy distribution in time and large chunks of the material will most likely sink to bottom as a single mass. We consider the description of the discharge in the model as a worst case. ...